PK0-004 · Question #729
A project manager needs to evaluate a suggested change order for a scope enhancement from a vendor on a project. To which of the following documents should the project manager refer?
The correct answer is A. RFI. A Request for Information (RFI) is the formal document through which a vendor submits a proposed change, clarification, or scope enhancement for review. When a vendor suggests a change order, it is typically submitted as - or documented within - an RFI, making it the primary…
Question
A project manager needs to evaluate a suggested change order for a scope enhancement from a vendor on a project. To which of the following documents should the project manager refer?
Options
- ARFI
- BPO
- CRFQ
- DSOW
How the community answered
(45 responses)- A93% (42)
- B2% (1)
- D4% (2)
Explanation
A Request for Information (RFI) is the formal document through which a vendor submits a proposed change, clarification, or scope enhancement for review. When a vendor suggests a change order, it is typically submitted as - or documented within - an RFI, making it the primary reference for evaluating the proposal. An SOW (Statement of Work) defines original scope but is not the mechanism for submitting changes. An RFQ (Request for Quote) is used to obtain pricing. A PO (Purchase Order) is used to authorize and confirm purchases of goods or services.