While working with a project team to create the project schedule, which of the following must occur for performance measurement?
The correct answer is D. Set the baseline. The project management plan contains the project management baseline data (typically cost, schedule, and scope), which you’ll use to monitor and compare performance measurements
Project life cycle phases
Question
While working with a project team to create the project schedule, which of the following must occur for performance measurement?
Options
- AIdentify resource costs
- BManage issues
- CCreate status reports
- DSet the baseline
How the community answered
(38 responses)- A3% (1)
- B5% (2)
- D92% (35)
Explanation
The project management plan contains the project management baseline data (typically cost, schedule, and scope), which you’ll use to monitor and compare performance measurements
Topics
#schedule baseline#performance measurement#planning phase#project schedule