nerdexam
CompTIA

PK0-004 · Question #693

While working with a project team to create the project schedule, which of the following must occur for performance measurement?

The correct answer is D. Set the baseline. The project management plan contains the project management baseline data (typically cost, schedule, and scope), which you’ll use to monitor and compare performance measurements

Project life cycle phases

Question

While working with a project team to create the project schedule, which of the following must occur for performance measurement?

Options

  • AIdentify resource costs
  • BManage issues
  • CCreate status reports
  • DSet the baseline

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    5% (2)
  • D
    92% (35)

Explanation

The project management plan contains the project management baseline data (typically cost, schedule, and scope), which you’ll use to monitor and compare performance measurements

Topics

#schedule baseline#performance measurement#planning phase#project schedule

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice