PK0-004 · Question #692
Which of the following should be used to identify where slack is occurring in the project schedule and determine the critical path? (Choose two.)
The correct answer is A. PERT chart C. Arrow diagram method. An arrow diagram is a variation of the PERT chart. They are both used for the sequencing of events & discovering task dependencies. A fishbone diagram is used to find the root cause of a major issue within the project. Slack is not an issue, they just need to find where they…
Question
Which of the following should be used to identify where slack is occurring in the project schedule and determine the critical path? (Choose two.)
Options
- APERT chart
- BRisk register
- CArrow diagram method
- DRACI matrix
- EProject charter
- FFishbone diagram
How the community answered
(32 responses)- A88% (28)
- B6% (2)
- D3% (1)
- F3% (1)
Explanation
An arrow diagram is a variation of the PERT chart. They are both used for the sequencing of events & discovering task dependencies. A fishbone diagram is used to find the root cause of a major issue within the project. Slack is not an issue, they just need to find where they have available slack while calculating the critical path.