PK0-004 · Question #687

Which of the following documents focus primarily on support activities after the completion of a project? (Choose two.)

The correct answer is A. Warranty B. SLA. A warranty is a commitment by the vendor or project team to repair or replace defective deliverables after handoff, making it a post-project support document. A Service Level Agreement (SLA) defines the ongoing performance standards (uptime, response times, support levels) that…

Tools and documentation

Question

Which of the following documents focus primarily on support activities after the completion of a project? (Choose two.)

Options

  • AWarranty
  • BSLA
  • CPurchase order
  • DLetter of intent
  • ERFQ
  • FIMS

How the community answered

(29 responses)
  • A
    90% (26)
  • C
    7% (2)
  • D
    3% (1)

Explanation

A warranty is a commitment by the vendor or project team to repair or replace defective deliverables after handoff, making it a post-project support document. A Service Level Agreement (SLA) defines the ongoing performance standards (uptime, response times, support levels) that must be maintained after the project delivers a product or service - it is inherently a post-completion operations document. A purchase order is a procurement instrument used during the project. A letter of intent signals early-stage intent to contract. An RFQ (Request for Quotation) is used during vendor selection. An IMS (Integrated Master Schedule) is a planning and tracking tool used during project execution.

Topics

#warranty#SLA#post-project support#project closure