PK0-004 · Question #687

PK0-004 Question #687: Real Exam Question with Answer & Explanation

The correct answer is A: Warranty. A warranty is a commitment by the vendor or project team to repair or replace defective deliverables after handoff, making it a post-project support document. A Service Level Agreement (SLA) defines the ongoing performance standards (uptime, response times, support levels) that m

Question

Which of the following documents focus primarily on support activities after the completion of a project? (Choose two.)

Options

  • AWarranty
  • BSLA
  • CPurchase order
  • DLetter of intent
  • ERFQ
  • FIMS

Explanation

A warranty is a commitment by the vendor or project team to repair or replace defective deliverables after handoff, making it a post-project support document. A Service Level Agreement (SLA) defines the ongoing performance standards (uptime, response times, support levels) that must be maintained after the project delivers a product or service - it is inherently a post-completion operations document. A purchase order is a procurement instrument used during the project. A letter of intent signals early-stage intent to contract. An RFQ (Request for Quotation) is used during vendor selection. An IMS (Integrated Master Schedule) is a planning and tracking tool used during project execution.