CompTIA
PK0-004 · Question #68
PK0-004 Question #68: Real Exam Question with Answer & Explanation
The correct answer is A: A list of realized risks. Risks that have actually occurred are tracked as realized risks in the risk register, not as planned activities or communication logs.
Question
A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave. Which of the following should a project manager update to document this information?
Options
- AA list of realized risks
- BA list of decomposed activities
- CA sequenced list of project tasks
- DA document describing agreed-upon communication methods
Explanation
Risks that have actually occurred are tracked as realized risks in the risk register, not as planned activities or communication logs.
Common mistakes.
- B. A list of decomposed activities is part of the work breakdown structure and records tasks, not risk occurrences.
- C. A sequenced list of project tasks is the project schedule, which orders activities rather than documenting risk events.
- D. A document describing agreed-upon communication methods defines how the team shares information, not where risk occurrences are recorded.
Concept tested. Documenting realized risks in the risk register
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Community Discussion
No community discussion yet for this question.