PK0-004 · Question #68

A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to…

The correct answer is A. A list of realized risks. Risks that have actually occurred are tracked as realized risks in the risk register, not as planned activities or communication logs.

Tools and documentation

Question

A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave. Which of the following should a project manager update to document this information?

Options

  • AA list of realized risks
  • BA list of decomposed activities
  • CA sequenced list of project tasks
  • DA document describing agreed-upon communication methods

How the community answered

(58 responses)
  • A
    90% (52)
  • B
    2% (1)
  • C
    7% (4)
  • D
    2% (1)

Why each option

Risks that have actually occurred are tracked as realized risks in the risk register, not as planned activities or communication logs.

AA list of realized risksCorrect

A list of realized risks (also called the risk register's realized or triggered risks section) documents issues that have materialized during project execution. The datacenter being inaccessible and the team member being on medical leave are both risk events that have already occurred, making them realized risks. Recording them here ensures the project manager can track impacts, initiate responses, and update forecasts accordingly.

BA list of decomposed activities

A list of decomposed activities is part of the work breakdown structure and records tasks, not risk occurrences.

CA sequenced list of project tasks

A sequenced list of project tasks is the project schedule, which orders activities rather than documenting risk events.

DA document describing agreed-upon communication methods

A document describing agreed-upon communication methods defines how the team shares information, not where risk occurrences are recorded.

Concept tested: Documenting realized risks in the risk register

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#risk management#issue log#realized risks#risk documentation