PK0-004 · Question #671

During a weekly meeting, a project manager mentioned a decision was made on June 17 to include future state workflows in onboard training. Which of the following communication methods should be used?

The correct answer is C. Project schedule. The decision to add future state workflows to onboard training is an action that affects the project timeline-it represents a new activity that must be planned and tracked. The project schedule is the appropriate artifact for capturing when specific activities are added…

Tools and documentation

Question

During a weekly meeting, a project manager mentioned a decision was made on June 17 to include future state workflows in onboard training. Which of the following communication methods should be used?

Options

  • AProject communications plan
  • BProject dashboard
  • CProject schedule
  • DProject status report

How the community answered

(32 responses)
  • B
    6% (2)
  • C
    91% (29)
  • D
    3% (1)

Explanation

The decision to add future state workflows to onboard training is an action that affects the project timeline-it represents a new activity that must be planned and tracked. The project schedule is the appropriate artifact for capturing when specific activities are added, assigned, and planned for completion, anchored to a specific date (June 17). The project communications plan (A) governs how communications are managed, not where decisions are recorded. A project dashboard (B) provides high-level status at a point in time. A project status report (D) summarizes overall progress but is a periodic snapshot, not the tracking document for scheduling a new deliverable.

Topics

#communication methods#meeting documentation#project schedule#decision tracking