PK0-004 · Question #669
A project manager wants to determine the percentage of a project's budgeted costs versus expenditures. Which of the following calculations should the project manager perform?
The correct answer is A. Burn rate. Expenditure tracking includes measuring the project spending to date, determining the burn rate (or how fast you’re going through the money), and tracking expenditures to the cost baseline so that stakeholders can see what was planned versus what was actually spent on the…
Question
A project manager wants to determine the percentage of a project's budgeted costs versus expenditures. Which of the following calculations should the project manager perform?
Options
- ABurn rate
- BCritical path analysis
- CEV
- DEAC
How the community answered
(37 responses)- A89% (33)
- B5% (2)
- C3% (1)
- D3% (1)
Explanation
Expenditure tracking includes measuring the project spending to date, determining the burn rate (or how fast you’re going through the money), and tracking expenditures to the cost baseline so that stakeholders can see what was planned versus what was actually spent on the project.