PK0-004 · Question #668

PK0-004 Question #668: Real Exam Question with Answer & Explanation

The correct answer is C: Gantt chart. Gantt charts can show milestones, deliverables, and all the activities of the project including their durations, start and end dates, and the resources assigned to the task. Gantt charts typically display the tasks using a horizontal bar chart format across a timeline. I know pro

Question

Which of the following is MOST commonly associated with the WBS and used to develop a project timeline?

Options

  • AProcess diagram
  • BRACI matrix
  • CGantt chart
  • DNetwork diagram

Explanation

Gantt charts can show milestones, deliverables, and all the activities of the project including their durations, start and end dates, and the resources assigned to the task. Gantt charts typically display the tasks using a horizontal bar chart format across a timeline. I know project managers who have constructed Gantt charts for small projects using only a spreadsheet.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice