nerdexam
ExamsPK0-004Questions#653
CompTIA

PK0-004 · Question #653

PK0-004 Question #653: Real Exam Question with Answer & Explanation

The correct answer is C: WBS. A hierarchical decomposition of a project into phases, deliverables, and work packages is the defining structure of a Work Breakdown Structure (WBS).

Question

Given the table below for a house construction project: The table above is an example of which of the following project artifacts?

Options

  • AProject plan
  • BSOW
  • CWBS
  • DRTM
  • ERBS
  • FStatus report

Explanation

A hierarchical decomposition of a project into phases, deliverables, and work packages is the defining structure of a Work Breakdown Structure (WBS).

Common mistakes.

  • A. A project plan is a broader document encompassing schedule, budget, resources, and risk - not a hierarchical decomposition table.
  • B. A Statement of Work (SOW) is a narrative document describing the work to be performed, deliverables, and timelines, not a hierarchical breakdown.
  • D. A Requirements Traceability Matrix (RTM) maps requirements to test cases and deliverables to ensure coverage, not a hierarchical task decomposition.
  • E. A Resource Breakdown Structure (RBS) organizes resources by type or category, not project deliverables or tasks.
  • F. A status report communicates current project progress and issues, not a structured decomposition of project scope.

Concept tested. Work Breakdown Structure identification

Reference. https://www.pmi.org/learning/library/applying-work-breakdown-structure-project-lifecycle-4961

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice