Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop. Which of the following steps should the…

The correct answer is B. Have Ann submit a change request. The requirement for a laptop has changed to a tablet. Therefore, Ann has to submit a change

Project life cycle phases

Question

Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop. Which of the following steps should the project manager take NEXT?

Options

  • ASupply Ann with the requested tablet.
  • BHave Ann submit a change request.
  • CProvide Ann with a copy of the project management plan.
  • DInform Ann that she will receive what has been authorized.

How the community answered

(43 responses)
  • A
    2% (1)
  • B
    88% (38)
  • C
    2% (1)
  • D
    7% (3)

Explanation

The requirement for a laptop has changed to a tablet. Therefore, Ann has to submit a change

Topics

#change request#scope management#change control process#customer requests