Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop. Which of the following steps should the…
The correct answer is B. Have Ann submit a change request. The requirement for a laptop has changed to a tablet. Therefore, Ann has to submit a change
Project life cycle phases
Question
Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop. Which of the following steps should the project manager take NEXT?
Options
- ASupply Ann with the requested tablet.
- BHave Ann submit a change request.
- CProvide Ann with a copy of the project management plan.
- DInform Ann that she will receive what has been authorized.
How the community answered
(43 responses)- A2% (1)
- B88% (38)
- C2% (1)
- D7% (3)
Explanation
The requirement for a laptop has changed to a tablet. Therefore, Ann has to submit a change
Topics
#change request#scope management#change control process#customer requests