PK0-004 · Question #646

A project, which is nearing completion, is ahead of schedule and under budget. However, to improve quality to acceptable levels, the project will require additional time. Which of the following BEST…

The correct answer is C. Constraint reprioritization. When improving one project constraint (quality) requires sacrificing another (time), the project manager must reprioritize which constraint takes precedence. This is the definition of constraint reprioritization.

Project management concepts

Question

A project, which is nearing completion, is ahead of schedule and under budget. However, to improve quality to acceptable levels, the project will require additional time. Which of the following BEST describes this scenario?

Options

  • AScore creep
  • BInteractions between constraints
  • CConstraint reprioritization
  • DChange request

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    9% (3)
  • C
    83% (29)
  • D
    6% (2)

Why each option

When improving one project constraint (quality) requires sacrificing another (time), the project manager must reprioritize which constraint takes precedence. This is the definition of constraint reprioritization.

AScore creep

Score creep is not a standard project management term - scope creep refers to uncontrolled expansion of project scope, which is not described here.

BInteractions between constraints

Interactions between constraints describes the general relationship between constraints, not the deliberate decision to adjust their priorities.

CConstraint reprioritizationCorrect

Constraint reprioritization occurs when the project team or sponsor consciously decides to adjust the priority of competing constraints - in this case, deprioritizing the schedule advantage in favor of meeting quality standards. The triple constraint model (scope, schedule, cost, quality) means improving one area often requires trading off another, and a deliberate decision to do so represents reprioritization.

DChange request

A change request is a formal document submitted to request a modification, but the scenario describes the broader decision-making situation, not a specific formal request artifact.

Concept tested: Triple constraint trade-off and reprioritization

Source: https://www.pmi.org/learning/library/triple-constraint-erroneous-useless-value-8024

Topics

#project constraints#triple constraint#quality management#constraint reprioritization