nerdexam
CompTIA

PK0-004 · Question #642

Given the following: Which of the following is the duration of the critical path?

The correct answer is C. 38 days. Task 1 (1 day) - Task 2 (3 days) - Task 4 (9 days) - Task 7 (10 days) - Task 9 (15 days) 1 + 3 + 9 + 10+ 15 = 38

Tools and documentation

Question

Given the following:

Which of the following is the duration of the critical path?

Exhibits

PK0-004 question #642 exhibit 1
PK0-004 question #642 exhibit 2
PK0-004 question #642 exhibit 3

Options

  • A35 days
  • B37 days
  • C38 days
  • D72 days
  • E73 days

How the community answered

(51 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    82% (42)
  • D
    10% (5)
  • E
    4% (2)

Explanation

Task 1 (1 day) - Task 2 (3 days) - Task 4 (9 days) - Task 7 (10 days) - Task 9 (15 days) 1 + 3 + 9 + 10+ 15 = 38

Topics

#critical path#network diagram#schedule management#duration calculation

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice