nerdexam
ExamsPK0-004Questions#642
CompTIA

PK0-004 · Question #642

PK0-004 Question #642: Real Exam Question with Answer & Explanation

The correct answer is C: 38 days. Task 1 (1 day) - Task 2 (3 days) - Task 4 (9 days) - Task 7 (10 days) - Task 9 (15 days) 1 + 3 + 9 + 10+ 15 = 38

Question

Given the following: Which of the following is the duration of the critical path?

Exhibit

PK0-004 question #642 exhibit

Options

  • A35 days
  • B37 days
  • C38 days
  • D72 days
  • E73 days

Explanation

Task 1 (1 day) - Task 2 (3 days) - Task 4 (9 days) - Task 7 (10 days) - Task 9 (15 days) 1 + 3 + 9 + 10+ 15 = 38

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice