CompTIA
PK0-004 · Question #642
PK0-004 Question #642: Real Exam Question with Answer & Explanation
The correct answer is C: 38 days. Task 1 (1 day) - Task 2 (3 days) - Task 4 (9 days) - Task 7 (10 days) - Task 9 (15 days) 1 + 3 + 9 + 10+ 15 = 38
Question
Given the following: Which of the following is the duration of the critical path?
Exhibit
Options
- A35 days
- B37 days
- C38 days
- D72 days
- E73 days
Explanation
Task 1 (1 day) - Task 2 (3 days) - Task 4 (9 days) - Task 7 (10 days) - Task 9 (15 days) 1 + 3 + 9 + 10+ 15 = 38
Community Discussion
No community discussion yet for this question.
