PK0-004 · Question #642
Given the following: Which of the following is the duration of the critical path?
The correct answer is C. 38 days. Task 1 (1 day) - Task 2 (3 days) - Task 4 (9 days) - Task 7 (10 days) - Task 9 (15 days) 1 + 3 + 9 + 10+ 15 = 38
Tools and documentation
Question
Given the following:
Which of the following is the duration of the critical path?
Exhibits
Options
- A35 days
- B37 days
- C38 days
- D72 days
- E73 days
How the community answered
(51 responses)- A2% (1)
- B2% (1)
- C82% (42)
- D10% (5)
- E4% (2)
Explanation
Task 1 (1 day) - Task 2 (3 days) - Task 4 (9 days) - Task 7 (10 days) - Task 9 (15 days) 1 + 3 + 9 + 10+ 15 = 38
Topics
#critical path#network diagram#schedule management#duration calculation