PK0-004 · Question #625
A project manager has gathered time estimates for a new project's activities and is now ready to begin developing the schedule. Which of the following would the project manager most likely do NEXT?
The correct answer is B. Determine predecessors and dependencies. After time estimates are collected, the next step in schedule development is to define activity relationships by establishing predecessors and dependencies before sequencing can occur.
Question
A project manager has gathered time estimates for a new project's activities and is now ready to begin developing the schedule. Which of the following would the project manager most likely do NEXT?
Options
- ACreate a WBS.
- BDetermine predecessors and dependencies.
- CDetermine the critical path.
- DPrioritize tasks.
How the community answered
(20 responses)- A5% (1)
- B85% (17)
- D10% (2)
Why each option
After time estimates are collected, the next step in schedule development is to define activity relationships by establishing predecessors and dependencies before sequencing can occur.
A WBS is created earlier in the planning phase before time estimates are gathered, so it would already exist at this stage.
Determining predecessors and dependencies is required before a schedule network can be built - without knowing which activities must precede or follow others, it is impossible to sequence tasks, calculate durations along a path, or identify the critical path.
Determining the critical path requires that activity sequences and dependencies already be fully defined, so it cannot come before establishing predecessors.
Prioritizing tasks is not a formal schedule development step; activity sequencing through dependency definition fulfills this function within scheduling methodology.
Concept tested: Schedule development - activity sequencing and dependencies