PK0-004 · Question #626
Joe, a stakeholder, threatens to withdraw from a project that is not going according to his wishes. The president talks to the project manager regarding options for a response to the stakeholder…
The correct answer is A. Accept. When a project moves forward as originally planned despite a stakeholder threat, the team has chosen the Accept risk response strategy.
Question
Joe, a stakeholder, threatens to withdraw from a project that is not going according to his wishes. The president talks to the project manager regarding options for a response to the stakeholder, and they decide the project will move forward as originally planned. Which of the following risk strategies was used?
Options
- AAccept
- BMitigate
- CAvoid
- DTransfer
How the community answered
(57 responses)- A79% (45)
- B12% (7)
- C5% (3)
- D4% (2)
Why each option
When a project moves forward as originally planned despite a stakeholder threat, the team has chosen the Accept risk response strategy.
The Accept strategy means acknowledging a risk and deliberately choosing not to alter the project plan in response - the president and project manager reviewed the stakeholder's threat and decided to proceed as planned, accepting the potential consequence of the stakeholder's withdrawal without making any plan changes.
Mitigate involves taking proactive actions to reduce the probability or impact of a risk, which was not done here.
Avoid requires changing the project plan to eliminate the risk entirely, but the team explicitly chose to keep the original plan intact.
Transfer shifts the financial or operational risk to a third party such as through insurance or a contract clause, which was not the strategy employed.
Concept tested: Risk response strategies - Accept