A project has just begun, and people are not clear about the objectives. Which of the following meeting types is needed?
The correct answer is D. Kickoff. The kickoff meeting orients the team about the project's objectives and the clients' requirements.
Project life cycle phases
Question
A project has just begun, and people are not clear about the objectives. Which of the following meeting types is needed?
Options
- AStand-up
- BScheduling
- CImpromptu
- DKickoff
How the community answered
(33 responses)- A3% (1)
- C6% (2)
- D91% (30)
Explanation
The kickoff meeting orients the team about the project's objectives and the clients' requirements.