A project has just begun, and people are not clear about the objectives. Which of the following meeting types is needed?

The correct answer is D. Kickoff. The kickoff meeting orients the team about the project's objectives and the clients' requirements.

Project life cycle phases

Question

A project has just begun, and people are not clear about the objectives. Which of the following meeting types is needed?

Options

  • AStand-up
  • BScheduling
  • CImpromptu
  • DKickoff

How the community answered

(33 responses)
  • A
    3% (1)
  • C
    6% (2)
  • D
    91% (30)

Explanation

The kickoff meeting orients the team about the project's objectives and the clients' requirements.

Topics

#kickoff meeting#project initiation#meeting types#project objectives