A project team lacks the necessary team members to complete a project. The project manager has rejected numerous candidates. This is an example of:

The correct answer is B. low-quality resources. The project manager has rejected numerous candidates because of low-quality resources.

Project management concepts

Question

A project team lacks the necessary team members to complete a project. The project manager has rejected numerous candidates. This is an example of:

Options

  • Aoutsourcing.
  • Blow-quality resources.
  • Cbenched candidates.
  • Dresource planning.

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    89% (34)
  • C
    5% (2)
  • D
    3% (1)

Explanation

The project manager has rejected numerous candidates because of low-quality resources.

Topics

#resource management#resource quality#team building#staffing