CompTIA
PK0-004 · Question #609
A project team lacks the necessary team members to complete a project. The project manager has rejected numerous candidates. This is an example of:
The correct answer is B. low-quality resources. The project manager has rejected numerous candidates because of low-quality resources.
Project management concepts
Question
A project team lacks the necessary team members to complete a project. The project manager has rejected numerous candidates. This is an example of:
Options
- Aoutsourcing.
- Blow-quality resources.
- Cbenched candidates.
- Dresource planning.
How the community answered
(38 responses)- A3% (1)
- B89% (34)
- C5% (2)
- D3% (1)
Explanation
The project manager has rejected numerous candidates because of low-quality resources.
Topics
#resource management#resource quality#team building#staffing