A project manager is overseeing the construction of a new building. There are likely existing underground water, gas, and electrical lines. Which of the following is an example of mitigation?

The correct answer is D. Ensure the contractor has the appropriate utility maps. Risk mitigation involves taking proactive steps to reduce the probability or impact of a risk before it occurs. Providing the contractor with accurate utility maps reduces the likelihood of accidentally hitting underground lines - directly mitigating the risk. Option A (trust)…

Project management concepts

Question

A project manager is overseeing the construction of a new building. There are likely existing underground water, gas, and electrical lines. Which of the following is an example of mitigation?

Options

  • ATrust the contractor to do the job well because the company has been in business for a long time.
  • BTell the contractor that the company is responsible for any damage done to underground lines.
  • CImmediately fix any broken lines that are hit during construction.
  • DEnsure the contractor has the appropriate utility maps.

How the community answered

(40 responses)
  • A
    13% (5)
  • B
    10% (4)
  • C
    5% (2)
  • D
    73% (29)

Explanation

Risk mitigation involves taking proactive steps to reduce the probability or impact of a risk before it occurs. Providing the contractor with accurate utility maps reduces the likelihood of accidentally hitting underground lines - directly mitigating the risk. Option A (trust) is risk acceptance with no action. Option B (assigning liability to the contractor) is risk transference, not mitigation. Option C (fixing broken lines) is a corrective action taken after the risk has already materialized, making it a contingency response, not mitigation.

Topics

#risk mitigation#risk response#proactive planning#construction risk