A project manager has received documented approval from management to begin a project and the authority to start assigning resources to the project. The project manager has received the:
The correct answer is A. project charter. The project charter is the document that officially confirms the authority of project manager.
Project life cycle phases
Question
A project manager has received documented approval from management to begin a project and the authority to start assigning resources to the project. The project manager has received the:
Options
- Aproject charter.
- Bstatement of work.
- Cproject plan.
- Dproject request.
How the community answered
(51 responses)- A94% (48)
- C2% (1)
- D4% (2)
Explanation
The project charter is the document that officially confirms the authority of project manager.
Topics
#project charter#project authorization#project initiation#sponsor approval