PK0-004 · Question #603

A project manager has received documented approval from management to begin a project and the authority to start assigning resources to the project. The project manager has received the:

The correct answer is A. project charter. The project charter is the document that officially confirms the authority of project manager.

Project life cycle phases

Question

A project manager has received documented approval from management to begin a project and the authority to start assigning resources to the project. The project manager has received the:

Options

  • Aproject charter.
  • Bstatement of work.
  • Cproject plan.
  • Dproject request.

How the community answered

(51 responses)
  • A
    94% (48)
  • C
    2% (1)
  • D
    4% (2)

Explanation

The project charter is the document that officially confirms the authority of project manager.

Topics

#project charter#project authorization#project initiation#sponsor approval