PK0-004 · Question #593

The PMO has removed a vendor from a project for inflating costs and failing to complete deliverables in a timely manner. The PMO received complaints that vendor resources missed appointments and…

The correct answer is C. Service level agreement F. Statement of work. To defend the vendor removal, the PMO needs documents that define the specific contractual obligations the vendor failed to meet. The Service Level Agreement (SLA) (C) explicitly defines performance standards such as response times, appointment adherence, and service quality…

Tools and documentation

Question

The PMO has removed a vendor from a project for inflating costs and failing to complete deliverables in a timely manner. The PMO received complaints that vendor resources missed appointments and provided poor service. The vendor has initiated a lawsuit against the PMO, asserting the vendor was operating within the terms of the current agreement. Which of the following documents should be reviewed by the PMO to support vendor removal? (Choose two.)

Options

  • ACommunication plan
  • BProject charter
  • CService level agreement
  • DProject management plan
  • EAction items
  • FStatement of work

How the community answered

(24 responses)
  • A
    4% (1)
  • C
    83% (20)
  • D
    8% (2)
  • E
    4% (1)

Explanation

To defend the vendor removal, the PMO needs documents that define the specific contractual obligations the vendor failed to meet. The Service Level Agreement (SLA) (C) explicitly defines performance standards such as response times, appointment adherence, and service quality metrics-directly addressing the complaints about missed appointments and poor service. The Statement of Work (SOW) (F) defines the scope of deliverables, timelines, and work requirements-directly relevant to the allegations of failed deliverables and inflated costs. The communication plan (A) governs how information is shared, not vendor performance. The project charter (B) is a high-level authorization document. Action items (E) are informal meeting notes. The project management plan (D) is broad and not specific to vendor contractual terms. The SLA and SOW together form the evidentiary foundation for justifying the vendor's removal.

Topics

#service level agreement#statement of work#vendor management#contract documents