PK0-004 · Question #592
PK0-004 Question #592: Real Exam Question with Answer & Explanation
The correct answer is D: Conduct an impact analysis to verify there is no collateral damage.. The team member bypassed the formal change control process by implementing a change without authorization. Even if the change appears logically sound, the project manager's first priority is to assess the impact of this unauthorized change on the rest of the project-schedule, bud
Question
Options
- ANotify the team that the change has been made.
- BUpdate the project management plan based on the change.
- CProceed to the next task in the project schedule.
- DConduct an impact analysis to verify there is no collateral damage.
Explanation
The team member bypassed the formal change control process by implementing a change without authorization. Even if the change appears logically sound, the project manager's first priority is to assess the impact of this unauthorized change on the rest of the project-schedule, budget, resources, dependencies, and other deliverables. This is the impact analysis. Notifying the team (A) comes after the impact is understood. Updating the project management plan (B) is a downstream step that follows the impact analysis and formal change approval. Proceeding to the next task (C) ignores the risk that collateral damage may have already occurred. The PM must act immediately to contain potential ripple effects before taking any further action.
Community Discussion
No community discussion yet for this question.