PK0-004 · Question #591
PK0-004 Question #591: Real Exam Question with Answer & Explanation
The correct answer is C: Establish and monitor trigger conditions.. Medium-rated risks do not require immediate escalation or heavy resource allocation, but they must not be ignored. The best practice is to establish trigger conditions-early warning signs that indicate a risk is becoming more likely or is about to materialize-and then actively mo
Question
Exhibit
Options
- AIncrease the contingency reserve.
- BAdd the risks to the watch list.
- CEstablish and monitor trigger conditions.
- DAssign the sponsor as the primary risk owner.
Explanation
Medium-rated risks do not require immediate escalation or heavy resource allocation, but they must not be ignored. The best practice is to establish trigger conditions-early warning signs that indicate a risk is becoming more likely or is about to materialize-and then actively monitor for them. This allows the team to respond proactively before a medium risk escalates. Increasing contingency reserves (A) is more appropriate for high-probability/high-impact risks. Adding risks to the watch list (B) is typically reserved for low-rated risks that need minimal tracking. Assigning the sponsor as the primary risk owner (D) is inappropriate; the sponsor should not be burdened with owning routine medium-level risks-that responsibility belongs to the project team.
Community Discussion
No community discussion yet for this question.