The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?

The correct answer is A. Identify task relationships. The Work Package has been completed (according to the question). The next step is to identify the relationships between activities.

Project life cycle phases

Question

The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?

Options

  • AIdentify task relationships.
  • BPut the resources on tasks.
  • CSet the quality gates.
  • DEstimate the work package.

How the community answered

(26 responses)
  • A
    85% (22)
  • B
    4% (1)
  • C
    8% (2)
  • D
    4% (1)

Explanation

The Work Package has been completed (according to the question). The next step is to identify the relationships between activities.

Topics

#WBS#work packages#task relationships#project planning sequence