PK0-004 · Question #533
The project manager is running a project in an organization with a strong PMO and a mature control process. Due to vendor delays, the project is scheduled to exceed the authorized timeline. The…
The correct answer is C. Initiate a change request. In an organization with a strong PMO and mature control processes, any deviation from the approved plan - including schedule compression techniques like fast-tracking - must go through formal change control. The NEXT step is to initiate a change request (C) so that the proposed…
Question
The project manager is running a project in an organization with a strong PMO and a mature control process. Due to vendor delays, the project is scheduled to exceed the authorized timeline. The project manager has discovered that fast-tracking two tasks will mitigate the issue. Which of the following should the project manager do NEXT?
Options
- AAnnounce the fast track to the project team.
- BModify the schedule
- CInitiate a change request.
- DObtain approval.
How the community answered
(49 responses)- A14% (7)
- B6% (3)
- C76% (37)
- D4% (2)
Explanation
In an organization with a strong PMO and mature control processes, any deviation from the approved plan - including schedule compression techniques like fast-tracking - must go through formal change control. The NEXT step is to initiate a change request (C) so that the proposed change can be reviewed, evaluated, and approved through the established process. Announcing it to the team (A) or modifying the schedule (B) before approval would bypass governance. Obtaining approval (D) comes after the change request is formally submitted and evaluated.