PK0-004 · Question #524
A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project…
The correct answer is B. Issue log. The issue log is the correct document to examine because it records problems, disruptions, and their status - including external events like natural disasters that affect project resources. Examining the issue log would show the hurricane was logged as a disrupting event…
Question
A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation. Which of the following documents should the project manager examine NEXT to provide an explanation?
Options
- AMeeting minutes
- BIssue log
- CProject schedule
- DBudget
How the community answered
(31 responses)- A3% (1)
- B81% (25)
- C3% (1)
- D13% (4)
Explanation
The issue log is the correct document to examine because it records problems, disruptions, and their status - including external events like natural disasters that affect project resources. Examining the issue log would show the hurricane was logged as a disrupting event explaining why resources became unavailable and the schedule slipped. Meeting minutes (A) might contain some relevant discussion but are not structured for root-cause explanations. The project schedule (C) shows the impact (delays) but not the cause. The budget (D) is unrelated to explaining a schedule delay. The issue log (B) directly connects the cause (hurricane) to the schedule impact.