nerdexam
CompTIA

PK0-004 · Question #523

A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take FIRST?

The correct answer is C. Determine the impact of the requested change. CompTIA's 5-step Change Management Process: 1 - Identification --- Stake holder has communicated the request to the PM. 2 - Documentation --- PM should estimate its impact on project cost, schedule and any other constraints and then document it as well and complete the Change…

Project management concepts

Question

A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take FIRST?

Options

  • ASubmit a change request to the CCB.
  • BImplement the change to the project.
  • CDetermine the impact of the requested change.
  • DUpdate the schedule to accommodate the change.

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    13% (5)
  • C
    79% (30)
  • D
    3% (1)

Explanation

CompTIA's 5-step Change Management Process: 1 - Identification --- Stake holder has communicated the request to the PM. 2 - Documentation --- PM should estimate its impact on project cost, schedule and any other constraints and then document it as well and complete the Change Request Form 3 - Analysis of impact --- CCB uses the documented PM impact estimate provided on the change request documentation. 4 - Course of action (approve/reject) 5 - Update related plans -- Communicate the changes to all involved.

Topics

#scope change#change management#impact assessment#stakeholder communication

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice