The correct answer is D: Project scheduling. Project scheduling. It is where you set predecessors, dependencies, and governance gates

Question

Which of the following includes setting governance gates as well as predecessors and dependencies?

Options

  • AProject communication
  • BProject constraints
  • CProject change control
  • DProject scheduling

Explanation

Project scheduling. It is where you set predecessors, dependencies, and governance gates