PK0-004 · Question #522
PK0-004 Question #522: Real Exam Question with Answer & Explanation
The correct answer is D: Project scheduling. Project scheduling. It is where you set predecessors, dependencies, and governance gates
Question
Which of the following includes setting governance gates as well as predecessors and dependencies?
Options
- AProject communication
- BProject constraints
- CProject change control
- DProject scheduling
Explanation
Project scheduling. It is where you set predecessors, dependencies, and governance gates