PK0-004 · Question #521
Which of the following can a project manager use to keep track of finances and ensure costs are accurately applied to a project?
The correct answer is B. Cost baseline. The cost baseline is the approved, time-phased budget that serves as the reference point against which actual project expenditures are measured. It allows the project manager to track spending over time, identify variances, and ensure costs are accurately attributed to the…
Question
Options
- APO numbers
- BCost baseline
- CBill of materials
- DWBS codes
How the community answered
(54 responses)- A7% (4)
- B87% (47)
- C2% (1)
- D4% (2)
Explanation
The cost baseline is the approved, time-phased budget that serves as the reference point against which actual project expenditures are measured. It allows the project manager to track spending over time, identify variances, and ensure costs are accurately attributed to the correct project activities. PO numbers (A) track individual purchase orders but do not provide a holistic financial picture. A bill of materials (C) lists components and quantities, not financial tracking. WBS codes (D) organize scope and work packages but are a structural tool - while they can be linked to costs, they are not the primary financial tracking mechanism.
Topics
Community Discussion
No community discussion yet for this question.