PK0-004 · Question #511

A project manager is starting a project on an unfamiliar technology. The document that is MOST likely to be created and distributed is an:

The correct answer is C. RFI. An RFI (Request for Information) is used when a project manager or organization needs to gather information about a technology, product, or vendor capability before making procurement decisions. Since the technology is unfamiliar, the project manager would issue an RFI to learn…

Tools and documentation

Question

A project manager is starting a project on an unfamiliar technology. The document that is MOST likely to be created and distributed is an:

Options

  • ARTM
  • BRFQ
  • CRFI
  • DRFP

How the community answered

(49 responses)
  • A
    6% (3)
  • B
    2% (1)
  • C
    88% (43)
  • D
    4% (2)

Explanation

An RFI (Request for Information) is used when a project manager or organization needs to gather information about a technology, product, or vendor capability before making procurement decisions. Since the technology is unfamiliar, the project manager would issue an RFI to learn what vendors offer and to better understand the solution space-this informs future procurement documents. An RTM (Requirements Traceability Matrix) tracks requirements to deliverables. An RFQ (Request for Quote) is used when requirements are known and you need pricing. An RFP (Request for Proposal) solicits vendor proposals for a defined need. RFI comes first in the procurement cycle when knowledge is lacking.

Topics

#RFI#procurement documents#information gathering#unfamiliar technology

Community Discussion

No community discussion yet for this question.