PK0-004 · Question #510

PK0-004 Question #510: Real Exam Question with Answer & Explanation

The correct answer is B: Burn rate. You also want to monitor the rate at which you are using up your budget, called the burn rate, to avoid running out of money before the scope has been completed.

Question

Which of the following is a component of the project cost control?

Options

  • AScope statement
  • BBurn rate
  • CMOU
  • DSLA

Explanation

You also want to monitor the rate at which you are using up your budget, called the burn rate, to avoid running out of money before the scope has been completed.