A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services. Which of the following documents will the company MOST likely…

The correct answer is B. RFI. The RFI is the document created by demand or buy side companies to obtain service and resource information from supply side companies.

Tools and documentation

Question

A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services. Which of the following documents will the company MOST likely release FIRST?

Options

  • ARFO
  • BRFI
  • CRFP
  • DRFQ

How the community answered

(18 responses)
  • B
    89% (16)
  • C
    6% (1)
  • D
    6% (1)

Explanation

The RFI is the document created by demand or buy side companies to obtain service and resource information from supply side companies.

Topics

#procurement#RFI#vendor selection#third-party services