PK0-004 · Question #440
Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do…
The correct answer is C. Determine procurement needs to meet the project demands. With a fixed budget, deadline, and defined deliverables already established, the project manager must next determine what resources, materials, and services need to be procured externally to fulfill those deliverables within the given constraints. Procurement planning is a…
Question
Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?
Options
- ADetermine the flexibility between the project constraints
- BHold a kick-off meeting with the project team
- CDetermine procurement needs to meet the project demands
- DCreate the risk register
How the community answered
(44 responses)- A5% (2)
- B11% (5)
- C77% (34)
- D7% (3)
Explanation
With a fixed budget, deadline, and defined deliverables already established, the project manager must next determine what resources, materials, and services need to be procured externally to fulfill those deliverables within the given constraints. Procurement planning is a foundational step that informs how the budget will be spent and what external dependencies exist. A kick-off meeting comes after sufficient planning is in place. Creating the risk register and analyzing constraint flexibility are important but follow after understanding what the project actually needs to procure and execute.