PK0-004 · Question #439
A project sponsor has requested documentation to determine the scheduled activities for a project that is running behind schedule. Which of the following documents should the project manager send to…
The correct answer is D. WBS. The Work Breakdown Structure (WBS) hierarchically decomposes the total scope of work into manageable components and activities, making it the go-to document for identifying all project activities. A RACI (Responsible, Accountable, Consulted, Informed) chart maps roles to tasks…
Question
A project sponsor has requested documentation to determine the scheduled activities for a project that is running behind schedule. Which of the following documents should the project manager send to the sponsor to quickly identify the project activities?
Options
- ARACI
- BSWOT
- CSOW
- DWBS
How the community answered
(33 responses)- A3% (1)
- B3% (1)
- C9% (3)
- D85% (28)
Explanation
The Work Breakdown Structure (WBS) hierarchically decomposes the total scope of work into manageable components and activities, making it the go-to document for identifying all project activities. A RACI (Responsible, Accountable, Consulted, Informed) chart maps roles to tasks but does not define the schedule. A SWOT analysis is a strategic planning tool unrelated to project scheduling. A Statement of Work (SOW) describes the scope at a high level but does not break down individual activities. The WBS directly shows all the work packages and activities that constitute the project.