A project scheduler has calculated the project's critical path. Which of the following activities would most likely occur NEXT?

The correct answer is B. Resource allocation. Calculating the critical path is a late-stage activity in schedule development. Before the critical path can be determined, task decomposition (breaking down work), dependency determination (sequencing), and task duration identification must already be complete - these are…

Project life cycle phases

Question

A project scheduler has calculated the project's critical path. Which of the following activities would most likely occur NEXT?

Options

  • AAdditional task decomposition
  • BResource allocation
  • CDependency determination
  • DTask duration identification

How the community answered

(29 responses)
  • B
    93% (27)
  • C
    3% (1)
  • D
    3% (1)

Explanation

Calculating the critical path is a late-stage activity in schedule development. Before the critical path can be determined, task decomposition (breaking down work), dependency determination (sequencing), and task duration identification must already be complete - these are prerequisites to the critical path calculation. Once the critical path is known and the schedule is finalized, the logical next step is resource allocation: assigning the right people, equipment, and materials to each task. This ensures the schedule is executable and resource constraints are accounted for.

Topics

#critical path#resource allocation#planning sequence#project scheduling