nerdexam
ExamsPK0-004Questions#431
CompTIA

PK0-004 · Question #431

PK0-004 Question #431: Real Exam Question with Answer & Explanation

The correct answer is B: Resource allocation. Calculating the critical path is a late-stage activity in schedule development. Before the critical path can be determined, task decomposition (breaking down work), dependency determination (sequencing), and task duration identification must already be complete - these are prereq

Question

A project scheduler has calculated the project's critical path. Which of the following activities would most likely occur NEXT?

Options

  • AAdditional task decomposition
  • BResource allocation
  • CDependency determination
  • DTask duration identification

Explanation

Calculating the critical path is a late-stage activity in schedule development. Before the critical path can be determined, task decomposition (breaking down work), dependency determination (sequencing), and task duration identification must already be complete - these are prerequisites to the critical path calculation. Once the critical path is known and the schedule is finalized, the logical next step is resource allocation: assigning the right people, equipment, and materials to each task. This ensures the schedule is executable and resource constraints are accounted for.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice