PK0-004 · Question #431
A project scheduler has calculated the project's critical path. Which of the following activities would most likely occur NEXT?
The correct answer is B. Resource allocation. Calculating the critical path is a late-stage activity in schedule development. Before the critical path can be determined, task decomposition (breaking down work), dependency determination (sequencing), and task duration identification must already be complete - these are…
Question
A project scheduler has calculated the project's critical path. Which of the following activities would most likely occur NEXT?
Options
- AAdditional task decomposition
- BResource allocation
- CDependency determination
- DTask duration identification
How the community answered
(29 responses)- B93% (27)
- C3% (1)
- D3% (1)
Explanation
Calculating the critical path is a late-stage activity in schedule development. Before the critical path can be determined, task decomposition (breaking down work), dependency determination (sequencing), and task duration identification must already be complete - these are prerequisites to the critical path calculation. Once the critical path is known and the schedule is finalized, the logical next step is resource allocation: assigning the right people, equipment, and materials to each task. This ensures the schedule is executable and resource constraints are accounted for.