nerdexam
ExamsPK0-004Questions#300
CompTIA

PK0-004 · Question #300

PK0-004 Question #300: Real Exam Question with Answer & Explanation

The correct answer is A: An activity with zero day duration. Milestones in a Gantt chart are represented as activities with zero duration because they mark a point in time, not a span of work.

Question

In a Gantt chart, how are milestones displayed?

Options

  • AAn activity with zero day duration
  • BAn activity with one day duration
  • CActivity-on-node with a finish-to-finish precedence
  • DEnd-to-end bar graph showing the time to complete a task

Explanation

Milestones in a Gantt chart are represented as activities with zero duration because they mark a point in time, not a span of work.

Common mistakes.

  • B. An activity with one-day duration represents an actual work task, not a milestone; milestones have no duration by definition.
  • C. Activity-on-node with finish-to-finish precedence describes a dependency relationship in a network diagram (PDM), not how milestones are displayed in a Gantt chart.
  • D. An end-to-end bar graph showing time to complete a task describes how regular schedule activities are displayed in a Gantt chart, not milestones.

Concept tested. Gantt chart milestone representation

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice