PK0-004 · Question #290
A project scope document should include which of the following items? (Select TWO).
The correct answer is C. Key performance indicators D. Detailed objectives. A project scope document defines what the project will deliver and how success is measured, making detailed objectives and key performance indicators core components.
Question
A project scope document should include which of the following items? (Select TWO).
Options
- ACost control
- BContinuous service improvements
- CKey performance indicators
- DDetailed objectives
- ERisk management plan
How the community answered
(31 responses)- A3% (1)
- C87% (27)
- E10% (3)
Why each option
A project scope document defines what the project will deliver and how success is measured, making detailed objectives and key performance indicators core components.
Cost control is a component of the project management plan or cost management plan, not the scope document.
Continuous service improvement is an ITIL service management concept and is not a standard component of a project scope document.
Key performance indicators are measurable criteria included in the scope document to define how project success will be evaluated against defined goals.
Detailed objectives specify exactly what the project must accomplish and set the boundaries of the project scope, making them a fundamental element of any scope document.
A risk management plan is a separate project planning document that outlines how risks will be identified and managed, not a part of the scope document.
Concept tested: Project scope document required components
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.