There is a high probability of a needed resource becoming unavailable. The project manager determines the impact to be low; therefore, the MOST likely response to the identified risk is to:

The correct answer is A. Accept it. When a risk has low impact, accepting it is the most appropriate response regardless of its probability, as the cost of other responses would outweigh the consequence of the risk occurring.

Project management concepts

Question

There is a high probability of a needed resource becoming unavailable. The project manager determines the impact to be low; therefore, the MOST likely response to the identified risk is to:

Options

  • AAccept it
  • BAvoid it
  • CMinimize it
  • DMitigate it

How the community answered

(43 responses)
  • A
    74% (32)
  • B
    7% (3)
  • C
    5% (2)
  • D
    14% (6)

Why each option

When a risk has low impact, accepting it is the most appropriate response regardless of its probability, as the cost of other responses would outweigh the consequence of the risk occurring.

AAccept itCorrect

Risk acceptance is the standard strategy when the impact of a risk is determined to be low. Even with high probability, investing resources to avoid, mitigate, or minimize the risk is not cost-effective when consequences are minimal. Acceptance acknowledges the risk exists and allows the project to continue without diverting resources to address it.

BAvoid it

Avoidance is reserved for risks with high impact, as it requires changing the project plan to eliminate the threat entirely, which is excessive for a low-impact risk.

CMinimize it

Minimizing the likelihood or impact of a risk requires active effort and resources, which is not justified when the impact has already been assessed as low.

DMitigate it

Mitigation involves taking steps to reduce the probability or impact of a risk, which is unnecessary when the impact has already been assessed as low.

Concept tested: Risk response strategy selection based on impact

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#risk response#risk acceptance#probability-impact matrix#risk assessment