PK0-004 · Question #285
Which of the following are included in a risk register? (Select TWO).
The correct answer is A. Project risk responses B. Identified risks. A risk register is a project document that captures identified risks and the planned responses assigned to each risk.
Question
Which of the following are included in a risk register? (Select TWO).
Options
- AProject risk responses
- BIdentified risks
- CMajor milestones
- DRisk analysis tools
- ERisk control board members
How the community answered
(48 responses)- A88% (42)
- C2% (1)
- D2% (1)
- E8% (4)
Why each option
A risk register is a project document that captures identified risks and the planned responses assigned to each risk.
Risk responses are a standard component of the risk register - they document the planned strategy (mitigate, avoid, transfer, or accept) assigned to each identified risk, ensuring the team knows how to react if a risk occurs.
Identified risks are the foundational entries of a risk register - every other field in the register (probability, impact, response) is tied to a specific risk that was formally recognized during the risk identification process.
Major milestones are documented in the project schedule or milestone list, not the risk register.
Risk analysis tools such as probability-impact matrices are methodologies used to analyze risks, not entries stored within the register itself.
Personnel roles and contacts belong in stakeholder registers, RACI charts, or communication plans - the risk register does not list board members or ownership rosters.
Concept tested: Components of a project risk register
Topics
Community Discussion
No community discussion yet for this question.