Which of the following are included in a risk register? (Select TWO).

The correct answer is A. Project risk responses B. Identified risks. A risk register is a project document that captures identified risks and the planned responses assigned to each risk.

Tools and documentation

Question

Which of the following are included in a risk register? (Select TWO).

Options

  • AProject risk responses
  • BIdentified risks
  • CMajor milestones
  • DRisk analysis tools
  • ERisk control board members

How the community answered

(48 responses)
  • A
    88% (42)
  • C
    2% (1)
  • D
    2% (1)
  • E
    8% (4)

Why each option

A risk register is a project document that captures identified risks and the planned responses assigned to each risk.

AProject risk responsesCorrect

Risk responses are a standard component of the risk register - they document the planned strategy (mitigate, avoid, transfer, or accept) assigned to each identified risk, ensuring the team knows how to react if a risk occurs.

BIdentified risksCorrect

Identified risks are the foundational entries of a risk register - every other field in the register (probability, impact, response) is tied to a specific risk that was formally recognized during the risk identification process.

CMajor milestones

Major milestones are documented in the project schedule or milestone list, not the risk register.

DRisk analysis tools

Risk analysis tools such as probability-impact matrices are methodologies used to analyze risks, not entries stored within the register itself.

ERisk control board members

Personnel roles and contacts belong in stakeholder registers, RACI charts, or communication plans - the risk register does not list board members or ownership rosters.

Concept tested: Components of a project risk register

Topics

#risk register#identified risks#risk responses#risk management