Which of the following are common components of a project transition plan? (Select TWO).
The correct answer is A. Extended support C. Ownership identification. A project transition plan formalizes the handoff of completed deliverables to operations, and ownership identification along with extended support are two of its core components.
Question
Which of the following are common components of a project transition plan? (Select TWO).
Options
- AExtended support
- BWork performance
- COwnership identification
- DRisk assessment
- EBudget analysis
How the community answered
(41 responses)- A90% (37)
- B2% (1)
- D5% (2)
- E2% (1)
Why each option
A project transition plan formalizes the handoff of completed deliverables to operations, and ownership identification along with extended support are two of its core components.
Extended support is a standard transition plan element that defines the assistance the project team or vendor will provide to operations staff after the project closes, ensuring continuity.
Work performance data is a monitoring and controlling artifact used to measure project progress during execution, not a component of a transition plan.
Ownership identification formally designates the individual or team responsible for maintaining and operating the project deliverables post-closure, establishing accountability for the transferred work.
Risk assessment is a planning-phase activity used to identify and prioritize project threats, not a standard element of a transition plan.
Budget analysis is a cost management activity performed during planning and monitoring phases, not a defining component of a transition plan.
Concept tested: Project transition plan components