PK0-004 · Question #279
During which of the following process groups is the project charter developed?
The correct answer is A. Pre-project setup. The project charter is developed during the Initiating process group (referred to as 'Pre-project setup' in some frameworks), which formally authorizes the project and defines high-level objectives.
Question
During which of the following process groups is the project charter developed?
Options
- APre-project setup
- BProject execution
- CProject planning
- DProject control
How the community answered
(24 responses)- A88% (21)
- B8% (2)
- D4% (1)
Why each option
The project charter is developed during the Initiating process group (referred to as 'Pre-project setup' in some frameworks), which formally authorizes the project and defines high-level objectives.
The project charter is created during the Initiating phase (pre-project setup), where the project is formally authorized, the project manager is assigned authority, and high-level scope, objectives, and stakeholders are identified. This document must exist before planning or execution can begin.
Project execution focuses on carrying out the work defined in the project management plan; the charter is a prerequisite and already exists by this stage.
Project planning produces the project management plan and subsidiary plans, but the charter - which authorizes the planning effort itself - must be completed first.
Project control (monitoring and controlling) involves tracking performance against baselines; the charter is an input to this phase, not an output.
Concept tested: Project charter development in Initiating process group
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok