CompTIA
PK0-004 · Question #168
A project manager has been asked to prepare and present a review of the execution phase. Which of the following is the BEST audience for this review?
The correct answer is D. Project team. Project team is responsible for the review at the end of the execution phase.
Project life cycle phases
Question
A project manager has been asked to prepare and present a review of the execution phase. Which of the following is the BEST audience for this review?
Options
- AVendors
- BKey stakeholders
- CResources
- DProject team
- EBusiness analysts
How the community answered
(44 responses)- A5% (2)
- B2% (1)
- C2% (1)
- D91% (40)
Explanation
Project team is responsible for the review at the end of the execution phase.
Topics
#execution phase#project review#phase gate#audience