Question
new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
Options
- AIdentify and document the risk.
- BEvaluate the impact and justification.
- CImplement the change.
- DUpdate the documents and plans.