PK0-004 · Question #166

A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule. Which of the following…

The correct answer is C. 49 days. 1 -> 10 ---> 12 ----\ 3 -/ |____> 20 ---/ 5+1+10+20+10+3 = 49 The first 2 tasks can be done simultaneously, so you count 5+1. Same with the tasks that takes 12 and 20 days, you add +20. making this 49.

Tools and documentation

Question

A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule. Which of the following calculations accurately shows the critical path?

Exhibits

PK0-004 question #166 exhibit 1
PK0-004 question #166 exhibit 2
PK0-004 question #166 exhibit 3

Options

  • A20 days
  • B39 days
  • C49 days
  • D52 days

How the community answered

(27 responses)
  • A
    15% (4)
  • B
    7% (2)
  • C
    48% (13)
  • D
    30% (8)

Explanation

1 -> 10 ---> 12 ----\ 3 -/ |____> 20 ---/ 5+1+10+20+10+3 = 49 The first 2 tasks can be done simultaneously, so you count 5+1. Same with the tasks that takes 12 and 20 days, you add +20. making this 49.

Topics

#critical path#network diagram#schedule calculation#project schedule