A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule. Which of the following…
The correct answer is C. 49 days. 1 -> 10 ---> 12 ----\ 3 -/ |____> 20 ---/ 5+1+10+20+10+3 = 49 The first 2 tasks can be done simultaneously, so you count 5+1. Same with the tasks that takes 12 and 20 days, you add +20. making this 49.
Tools and documentation
Question
A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule. Which of the following calculations accurately shows the critical path?
Exhibits
Options
- A20 days
- B39 days
- C49 days
- D52 days
How the community answered
(27 responses)- A15% (4)
- B7% (2)
- C48% (13)
- D30% (8)
Explanation
1 -> 10 ---> 12 ----\ 3 -/ |____> 20 ---/ 5+1+10+20+10+3 = 49 The first 2 tasks can be done simultaneously, so you count 5+1. Same with the tasks that takes 12 and 20 days, you add +20. making this 49.
Topics
#critical path#network diagram#schedule calculation#project schedule