A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?

The correct answer is B. SOW. The project manager should be involved in the process of creating the SOW to ensure accuracy of the project requirements. Vendors use the SOW to determine whether they are capable of producing the deliverables and to determine their interest in bidding on your project work.

Tools and documentation

Question

A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?

Options

  • ASLA
  • BSOW
  • CChange request
  • DRFP

How the community answered

(48 responses)
  • A
    6% (3)
  • B
    88% (42)
  • C
    4% (2)
  • D
    2% (1)

Explanation

The project manager should be involved in the process of creating the SOW to ensure accuracy of the project requirements. Vendors use the SOW to determine whether they are capable of producing the deliverables and to determine their interest in bidding on your project work.

Topics

#procurement#SOW#vendor management#RFP