A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?

The correct answer is B. Evaluate the impact of the change. Once the formal change request is submitted, the project manager or other designated party should evaluate the impact of the requested change.

Project management concepts

Question

A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?

Options

  • ASubmit a change request.
  • BEvaluate the impact of the change.
  • CGet approval from the CCB.
  • DCommunicate the change to stakeholders.

How the community answered

(42 responses)
  • A
    5% (2)
  • B
    81% (34)
  • C
    2% (1)
  • D
    12% (5)

Explanation

Once the formal change request is submitted, the project manager or other designated party should evaluate the impact of the requested change.

Topics

#change management#impact analysis#change control#scope creep