If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

The correct answer is B. The scheduler should obtain the current status from team members, apply it to the baseline. According to the PMBOK, the schedule baseline is the approved version of the schedule model that is used as a basis for comparison to the actual results.

Tools and documentation

Question

If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

Options

  • AThe project sponsor should obtain the current status from team members, put it into a
  • BThe scheduler should obtain the current status from team members, apply it to the baseline
  • CThe scheduler should obtain the current status from team members, update the project
  • DThe scheduler should obtain the current status from team members, update the risk register,

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    71% (27)
  • C
    18% (7)
  • D
    8% (3)

Explanation

According to the PMBOK, the schedule baseline is the approved version of the schedule model that is used as a basis for comparison to the actual results.

Topics

#project baseline#status reporting#schedule update#project tracking