PK0-004 · Question #1060

A media company is improving its performance to reach the figures proposed by the Chief Executive Officer. The government has launched a new set of commercial and advertising standards. There are…

The correct answer is C. Requirements change. The government launching new commercial and advertising standards is an external regulatory event that forces the organization to reassess what the projects must deliver. This is a requirements change - the conditions that the project output must satisfy have changed due to new…

Project life cycle phases

Question

A media company is improving its performance to reach the figures proposed by the Chief Executive Officer. The government has launched a new set of commercial and advertising standards. There are some projects that require reassessment. Which of the following changes is being described?

Options

  • AScope change
  • BResource change
  • CRequirements change
  • DQuality change

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    92% (22)

Explanation

The government launching new commercial and advertising standards is an external regulatory event that forces the organization to reassess what the projects must deliver. This is a requirements change - the conditions that the project output must satisfy have changed due to new legal or regulatory constraints. A scope change would involve adding or removing deliverables, a resource change would involve people or budget, and a quality change would involve standards for how well deliverables are built. Here, it's the governing rules that define what must be done that have changed.

Topics

#requirements change#regulatory compliance#external factors#scope management