Question
A project team is comprised of team members from several regions including North America, Europe, and Asia. The project manager wants to make sure all team members are involved in the project while minimizing scheduling concerns. Which of the following should the project manager use to BEST facilitate communication throughout the project?
Options
- AOne-on-one conversations
- BSocial media
- CInstant messaging
- DConference calls