nerdexam
ExamsPK0-004Questions#1049
CompTIA

PK0-004 · Question #1049

PK0-004 Question #1049: Real Exam Question with Answer & Explanation

The correct answer is C: Schedule. (C) Schedule will be impacted because a faster paver accelerates the paving work, compressing the project timeline and potentially requiring the schedule to be re-baselined. (D) Resources will be impacted because a new, specialized piece of equipment typically requires trained or

Question

The project manager for a highway project is informed the project sponsor has requested a new street paver that will operate faster but increase the overall cost. Which of the following will MOST likely be impacted? (Choose two.)

Options

  • AEnvironment
  • BQuality
  • CSchedule
  • DResources
  • ERequirements
  • FScope

Explanation

(C) Schedule will be impacted because a faster paver accelerates the paving work, compressing the project timeline and potentially requiring the schedule to be re-baselined. (D) Resources will be impacted because a new, specialized piece of equipment typically requires trained or certified operators, may change crew compositions, and introduces new logistics for fuel, maintenance, and parts - all of which alter the resource plan. While cost is explicitly stated as increasing (confirming the budget/cost impact), the question asks what will 'most likely' be impacted from the given choices - schedule compression from the faster equipment and resource changes from operating new machinery are the two most direct operational consequences.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice