nerdexam
ExamsPK0-004Questions#1021
CompTIA

PK0-004 · Question #1021

PK0-004 Question #1021: Real Exam Question with Answer & Explanation

The correct answer is D: Project sponsor and project charter. The document described-one that details the objective, constraints, budget, and authorizes the start of a project-is the project charter. The person who reviews and approves the project charter is the project sponsor, who has the authority and financial backing to formally author

Question

A project manager is meeting with a stakeholder to review and obtain approval for a document that details the objective, constraints, and budget, as well as authorizes the commencement of a project. Which of the following stakeholders is the project manager meeting with and which document is being reviewed?

Options

  • AProject team and SOW
  • BProject champion and business case
  • CProject scheduler and Gantt chart
  • DProject sponsor and project charter

Explanation

The document described-one that details the objective, constraints, budget, and authorizes the start of a project-is the project charter. The person who reviews and approves the project charter is the project sponsor, who has the authority and financial backing to formally authorize the project. A SOW (A) defines deliverables, a business case (B) justifies why the project should be done, and a Gantt chart (C) is a scheduling tool, none of which match the description.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice