A project manager is meeting with a stakeholder to review and obtain approval for a document that details the objective, constraints, and budget, as well as authorizes the commencement of a project…

The correct answer is D. Project sponsor and project charter. The document described-one that details the objective, constraints, budget, and authorizes the start of a project-is the project charter. The person who reviews and approves the project charter is the project sponsor, who has the authority and financial backing to formally…

Project life cycle phases

Question

A project manager is meeting with a stakeholder to review and obtain approval for a document that details the objective, constraints, and budget, as well as authorizes the commencement of a project. Which of the following stakeholders is the project manager meeting with and which document is being reviewed?

Options

  • AProject team and SOW
  • BProject champion and business case
  • CProject scheduler and Gantt chart
  • DProject sponsor and project charter

How the community answered

(20 responses)
  • B
    5% (1)
  • C
    5% (1)
  • D
    90% (18)

Explanation

The document described-one that details the objective, constraints, budget, and authorizes the start of a project-is the project charter. The person who reviews and approves the project charter is the project sponsor, who has the authority and financial backing to formally authorize the project. A SOW (A) defines deliverables, a business case (B) justifies why the project should be done, and a Gantt chart (C) is a scheduling tool, none of which match the description.

Topics

#project charter#project sponsor#project initiation#authorization