PK0-004 · Question #1022
PK0-004 Question #1022: Real Exam Question with Answer & Explanation
The correct answer is B: Project sponsor. When a quality issue is discovered during a deliverable audit, the project sponsor should be notified first because they have executive authority over the project, own the budget, and are ultimately accountable for project outcomes. Notifying the sponsor first ensures proper esca
Question
Options
- AProject team
- BProject sponsor
- CStakeholders
- DProject champion
- EProject management office
Explanation
When a quality issue is discovered during a deliverable audit, the project sponsor should be notified first because they have executive authority over the project, own the budget, and are ultimately accountable for project outcomes. Notifying the sponsor first ensures proper escalation and authorization before corrective actions are taken. The project team (A) would be notified afterward to implement fixes. Stakeholders (C), the champion (D), and the PMO (E) are secondary notifications that follow the sponsor's awareness and direction.
Community Discussion
No community discussion yet for this question.