nerdexam
CompTIA

PK0-004 · Question #1022

A project manager conducted an audit of project deliverables. During the audit, the project manager identified a deliverable that did not meet quality standards. Which of the following describes who…

The correct answer is B. Project sponsor. When a quality issue is discovered during a deliverable audit, the project sponsor should be notified first because they have executive authority over the project, own the budget, and are ultimately accountable for project outcomes. Notifying the sponsor first ensures proper…

Project management concepts

Question

A project manager conducted an audit of project deliverables. During the audit, the project manager identified a deliverable that did not meet quality standards. Which of the following describes who the project manager should notify FIRST?

Options

  • AProject team
  • BProject sponsor
  • CStakeholders
  • DProject champion
  • EProject management office

How the community answered

(48 responses)
  • A
    2% (1)
  • B
    77% (37)
  • C
    2% (1)
  • D
    13% (6)
  • E
    6% (3)

Explanation

When a quality issue is discovered during a deliverable audit, the project sponsor should be notified first because they have executive authority over the project, own the budget, and are ultimately accountable for project outcomes. Notifying the sponsor first ensures proper escalation and authorization before corrective actions are taken. The project team (A) would be notified afterward to implement fixes. Stakeholders (C), the champion (D), and the PMO (E) are secondary notifications that follow the sponsor's awareness and direction.

Topics

#quality audit#deliverable quality#escalation#project sponsor

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice